As many as half of the 700 quick-build modular houses approved by the Government to house Ukrainian refugees might not be completed by the end of 2023 over difficulties assessing suitable sites
A presentation by the Office of Public Works (OPW) prepared for a meeting of the Oireachtas Committee on Housing confirmed that 204 modular homes on five sites will begin to be handed over for occupation from next month.
It also indicated that a further 106 homes on two sites in Tullamore, Co Offaly and Rathdowney, Co Laois will be completed from August 2023.
However, the OPW has no up-to-date information on the expected completion dates of the remaining 370 quick-build homes promised by the Government to accommodate as many as 2,800 refugees.
South Korea detects signs of North Korea preparing more troops and weapons for Russia
Palantir partners with leading defence and tech companies to win US government contracts
Volodymyr Zelenskiy tells Ukraine’s diplomats to fight for Nato membership
Ukraine: Key events that shaped 2024 and will influence the conflict in 2025
[ Huge shortfall in beds for refugees predicted as hotels switch focus to touristsOpens in new window ]
In its presentation the OPW said further completions are “dependent on the availability and quality of sites on offer”.
It said “site feasibility is currently being assessed” and “some sites may not be viable”. Already two identified sites, in Co Waterford and in Co Cork, have been deemed unsuitable.
The Government approved the provision of 500 modular houses last summer and later increased the overall target to 700 units. The original completion date was November 2022 but the process has been beset by delays. The deadline was pushed back to the new year and then until May.
Photographs supplied by the OPW to the committee confirm that work is well-progressed on the five sites in phase one: in Mahon, Co Cork (64 units); Farnham Road, Co Cavan (28 units); Thurles, Co Tipperary (62 units); Claremorris, Co Mayo (28 units) and Doorly Park, Sligo (22 units).
The overall cost projection for the project is estimated to be €140 million. Earlier this year the OPW appealed to local authorities asking them to identify 10 additional “good sites”. As of now, there is no indication that those sites have been identified.
Members of the committee, chaired by Green Party TD Steven Matthews, will question OPW officials closely on this and if there is any prospect of the 700 units being completed by the end of 2023.
The goal of the modular homes project was to develop brand new housing “rapidly” to ease the refugee accommodation crisis.
However, speaking in the Dáil at the end of March, Taoiseach Leo Varadkar said: “As we’ve always learned in the past from modular and rapid build, it’s not so cheap and not so rapid.”
The number of Ukrainian refugees in the country is now close to 80,000. More than 63,000 have been accommodated in hotels, emergency rest centres or homes offered by members of the public.
In its opening statement to the committee, the semi-State forest company, Coillte, called for a change in regulations in Ireland to allow more use of wood in construction. “Our building regulations currently have a 10-metre height limit in the use of timber, which is only three storeys. Mass timber buildings of up to 24 stories are being constructed elsewhere, so the regulations must be changed in Ireland,” it said.
According to Coillte, 25 per cent of housing units in Ireland are being built with timber-frames whereas the figure is closer to 80 per cent in Scotland and even higher in Scandinavia. It is calling for a “meaningful” increase in the use of timber in construction, which “equates to a 2.5 times net carbon saving for each new home built”.